The project will improve the following aspects of TDWG operations:
- Web site for managing and documenting TDWG standards
- Open standards development process (based on models and experiences of other standards organisations such as IETF, Open GIS Consortium, W3C)
- Support and coordination activities for Subgroups
- Publicity for TDWG standards
- Development of reusable software components to support TDWG standards
- Implementation of a shared system for managing globally unique identifiers for biodiversity data elements
- Planning of long-term support requirements and securing appropriate long-term funding
Background
Donald Hobern and Stan Blum developed a successful proposal to the Gordon and Betty Moore Foundation for funding a 30 month project for a Team to help TDWG to modernize its infrastructure for supporting standards development, and to ensure that all of its working groups have well-managed processes, including documentation and software components where applicable. During this same period, the Team will identify the core activities for which TDWG will require ongoing support, and identify funding sources to support these activities.
Scope
The scope of the project is to provide recommendations to TDWG through the TDWG Executive Committee concerning the actions required for the modernisation of the structure and operation of TDWG in the process of developing biodiversity interoperability standards.
Core Members
Lee Belbin (lee (at-sign) tdwg.org)
Roger Hyam (roger (at-sign) tdwg.org)
Ricardo Pereira (ricardo (at-sign) tdwg.org)
Donald Hobern (d.hobern (at-sign) gbif.org)
Stan Blum (sblum (at-sign) calacademy.org)
Clients
TDWG and all client agencies dependent on TDWG standards, protocols and services.
Outcomes and Outputs
| 1 | Renewed call for participation in Process Subgroup (to discuss new TDWG process) | 11 Sep 05 | 11 Sep 05 | SB |
| 2 | Call for participants in GUID development | 13 Sep 05 | 13 Sep 05 | DH, RP |
| 3 | Establishment of TDWG architecture interest group. | 15 Sep 05 | 15 Sep 05 | RH |
| 4 | Summary of requirements for documentation and associated software | 5 Oct 05 | 5 Oct 05 | RH |
| 5 | Summary of requirements for collaboration environment | 7 Oct 05 | 7 Oct 05 | RP |
| 6 | Review paper: current TDWG process | 9 Oct 05 | 9 Oct 05 | LB, SB |
| 7 | Project plan and milestones agreed between TDWG Executive and TDWG Infrastructure Project Team | 10 Oct 05 | 10 Oct 05 | LB, SB |
| 8 | Broader announcement of Project | 11 Oct 05 | 11 Oct 05 | LB, RP, RH |
| 9 | Draft charter for Process subgroup | 12 Oct 05 | 28 Jan 06 | SB |
| 10 | Review paper: best practices in standards development organisations | 30 Nov 05 | 30 Nov 05 | LB, SB |
| 11 | Review paper: collaboration infrastructure requirements and technologies | 3 Dec 05 | 3 Dec 05 | RP |
| 12 | Process subgroup meeting to draft new TDWG process | 5 Dec 05 | 30 Jan 06 | LB, SB |
| 13 | Final report on requirements for documentation and associated software | 7 Dec 05 | 15 Dec 06 | RH |
| 14 | Decision point on outsourcing the development and testing of the collaborative environment | 10 Dec 05 | 10 Dec 05 | RP |
| 15 | Prioritised list for 2006 for populating standards documents | 15 Dec 05 | 23 Dec 05 | RH |
| 16 | Drafts of initial normative documents specified in documentation software strategy | 23 Dec 05 | | RH |
| 17 | Close of comments on review paper on the collaborative infrastructure requirements and technologies | 31 Dec 05 | 31 Dec 05 | RP |
| 18 | Final version: Collaboration infrastructure requirements and technologies report | 25 Jan 06 | 25 Jan 06 | RP |
| 19 | First workshop for GUID development | 1 Feb 06 | 1 Feb 06 | DH, RP |
| Added | TDWG Survey | 4 Feb 06 | 4 Feb 06 | LB |
| 20 | Purchase TDWG server & associated software | 5 Feb 06 | 1 Mar 06 | RP |
| 21 | First draft: new TDWG process | 7 Feb 06 | 4 Feb 06 | LB, SB |
| 22 | Draft architectural framework for TDWG released for comments and revision | 25 Mar 06 | April 11, 2006 | RH |
| 23 | Final version: new TDWG process | 1 Apr 06 | | LB, SB |
| 24 | Preliminary collaborative environment available for viewing and testing | 15 Apr 06 | 12 Apr 06 | RP |
| 25 | Synthesize recommendations from subgroups on GUIDs - review paper | 1 May 06 | | DH, RP |
| 26 | Close of comments on preliminary collaborative environment | 15 May 06 | 15 May 07 | RP |
| 27 | Approval by TDWG of the new process | 1 Jun 06 | | LB, SB |
| 28 | Architectural framework for TDWG released for voting | 3 Jun 06 | | RH |
| 29 | Second workshop for GUID development | 5 Jun 06 | 10 Jun 06 | DH, RP |
| 30 | Launch of the collaborative development environment | 15 Jul 06 | | RP |
| 31 | Adoption of architectural framework for TDWG | 1 Aug 06 | | RH |
| 32 | Document summarising progress against 2006 documentation work plan. | 1 Sep 06 | | RH |
| 33 | Implementation of first version of GUID infrastructure; First release of GUID systems | 1 Oct 06 | | DH, RP |
| 34 | Review paper: TDWG long-term goals and budgetary requirements | 5 Oct 06 | | LB |
| 35 | Meeting with TDWG Executive on funding brochure (draft) | 15 Nov 06 | | LB |
| 36 | Prioritised list for 2007 for populating standards documents | 1 Dec 06 | | RH |
| 37 | Funding brochure | 15 Jan 07 | | LB |
| 38 | Document summarising progress against 2007 documentation work plan. | 1 Sep 07 | | RH |
| 39 | Review paper: GUID systems review (TDWG 2006) based on first implementation | 5 Sep 07 | | DH, RP |
| 40 | Document reviewing options for long-term support and infrastructure | 1 Oct 07 | | LB |
| 41 | Adjustments and second release of GUID systems based on review | 15 Nov 07 | | DH, RP |
| 42 | Long-term support/infrastructure adopted | 1 Dec 07 | | LB |
Strategy
- Contract
- Project Manager
- Technical Architect
- Software Engineer
- Other subcontractors as required
- Develop milestones against project goals
- Maintain a high-level of effective communication with the TDWG membership through the TDWG Secretariat
- Deliver milestones (reports and recommendations) to the TDWG Executive for approval through current TDWG decisionmaking processes
Resources
TIP Wiki: http://wiki.tdwg.org/twiki/bin/view/TIP/WebHome
TIP Documents: http://wiki.tdwg.org/twiki/bin/view/TIP/TipDocuments
Version History
May 27, 2006 - Charter uploaded.
July 1st, 2005 - Project started.